AI Photonics · InP research update

InP is still the binding constraint. The 10% hike is a channel check, not a new fact.

經濟日報 (17 Aug 2026) says Q4 InP substrate / epi prices will rise more than 10% — “even with money you may not get it” — and names 全新 (VPEC 2455), 聯亞 (LandMark 3081) and IET-KY (4971). The tightness is independently confirmed by Coherent, Lumentum and Citi. The article is late to a tape that has already re-rated the Taiwan epi names 60–380% YTD.

As of 17 Aug 2026 Bloomberg snapshot · TWD/32, JPY/150 Source: 經濟日報 + Citi 16 Jul + LITE/COHR prints + MOPS Not investment advice
4th / 3rd
Substrate / epi hike count (trade press)
>10%
Claimed Q4 hike vs prior 3–5%
30 / 20 / 11%
Citi EML gap FY26–28
+379%
LandMark YTD — already priced

One-sentence take

InP wafers and the lasers grown on them remain the narrowest physical bottleneck in AI optics; the new 經濟日報 piece is a Taiwan-language amplification of a constraint LITE, COHR and Citi already described. What changed today is the claimed step-up in hike size (from 3–5% to >10%) and the explicit naming of the three Taiwan merchant epi houses. What did not change is the valuation: 3081 at 84x TTM sales / 138x FY27E EPS is no longer a discovery name.

Treat the 10% figure as an industry-source channel check (記者陳昱翔 quoting 業界人士), not a posted price list. The independently verified facts sit one layer down: long-term substrate lock-ups, COHR “primary constraint,” and Citi’s three-year EML deficit.

Claim-by-claim review of the 經濟日報 clip

ClaimVerdictIndependent check
InP substrate on a fourth consecutive hike; Q4 >10% Partial — trade press Single 經濟日報 source (17 Aug). Consistent with Citi (16 Jul) adding another 15% LITE FY27 price, and with China Feb-2025 export licenses that Citi said pushed 6-inch wafers ~+250% to ~$5,000. No company 公告 of a 10% list-price move.
Epi already hiked twice; Q4 heading for a third Partial — trade press Same article. LandMark 1Q26 GM 54.8% (8-year high, MS 22 Apr) shows mix/pricing already happened. Pass-through of a third hike is the open question, not whether prior hikes occurred.
“有錢也未必買得到” Directionally confirmed COHR 12 Aug: InP “primary constraint”; will not sell InP lasers externally because datacom “absorbs every bit of capacity.” Citi: EML deficit 30/20/11% in 2026–28. LITE 11 Aug: “pretty big surge… found additional substrate help from AXTI.”
COHR / LITE signed long-term upstream contracts Confirmed Already in the AIOT file: LITE prepaid AXTI $87m through 2031; COHR prepaid $22.3m. LITE’s Aug print reconfirmed the AXTI add-on. 招商通信 17 Aug: LITE signed an emergency AXT substrate LTA because UHP CW supply “far behind demand.”
全新 adding tools; Q3 monthly revenue rising Revenue confirmed MOPS/財報狗: Jul-26 NT$422m, +29.5% MoM / +45% YoY, fifth consecutive monthly rise, 40-month high. Tool-add is company color via 經濟日報, not a dated capex 公告 in this pass.
IET US fab phase 2 started last July, finishes this year Confirmed, slightly compressed Company: Texas phase 2 started Jul 2025, completion late-2026 to early-2027 (MoneyDJ 27 Jul 2026; 2025 法說). Article says “今年完工.”
聯亞 NT$13.15bn capex + Sumitomo Electric 5-year InP substrate LTA Confirmed MOPS 22 Apr 2026: 5-year contract 2026–2030 with 住友電氣工業; board also approved ≤NT$13.15bn equipment (front-end epi + litho/etch) for 2027H2 demand. Q2 EPS NT$4.62, record; 2027 capacity guided 2.5× (經濟日報 12–13 Aug).
光進銅退 as the reason InP is “the next memory” Overstated framing Scale-out still has a long copper / AEC / pluggable life (CRDO, 650 Group: CPO vs pluggable crossover ~2031). InP demand is real even if copper does not “retreat.” Do not underwrite the theme as a copper-replacement binary.

Source article: money.udn.com/money/story/5612/9695292 · 2026-08-17 02:01 HKT

Stack — what actually has to scale

indium / red phosphorus → InP substrate (AXTI · JX 5016 · Sumitomo 5802) → merchant epi (VPEC 2455 · LandMark 3081 · IET 4971 · IQE) → EML / CW / PD die (LITE · COHR · SEI · WIN 3105) → 800G / 1.6T module or ELS / CPO engine → GPU / switch rack

SiPh does not retire this stack. Silicon cannot emit at 1310/1550; every SiPh PIC still needs a hybrid or external InP laser. Citi (16 Jul) is explicit: InP demand climbs with AI bandwidth “regardless of how much ground silicon photonics gains for integration.”

If AI optical demand doubles, the first thing that breaks is qualified InP wafers and the high-power CW / EML die grown on them — not module assembly, not SOI, not DSP. That is unchanged from the June bottleneck note. The new information is that merchant epi in Taiwan is now being offered as the liquid expression of that tightness, after LITE/COHR already locked substrate.

Bloomberg snapshot · 17 Aug 2026

NameRolePriceMcap TTM P/STTM / FY27E P/E YTD1MStreet TP
VPEC 2455 TTMerchant III-V epi (mixed RF + optical) NT$417$2.4B20.4x 101x / 78x+175%+48% NT$430 (14 rec, 4.79)
LandMark 3081 TTMerchant InP/GaAs epi, SiPh mix rising NT$2,670$8.5B84.4x 262x / 138x+379%+80% NT$3,134 (15 rec, 4.47)
IET-KY 4971 TTMBE InP / APD-PIN epi NT$501$0.74B17.6x 98x / 62x+62%+34% NT$746 (5 rec, 3.60)
AXTI USInP substrate (China Tongmei) $81.64$5.4B33.5x n.m. / 94x+399%+78% $91.60 (5 rec, 4.60)
JX 5016 JPNon-China InP substrate ¥3,841$24.3B3.7x 26x / —+96%+8% ¥4,771 (13 rec)
SEI 5802 JPSubstrate + EML/CW, conglomerate ¥2,364$50.1B1.4x 18x / —+50%+5% ¥3,676 (13 rec)
LITE USEML / UHP CW / OCS $926$82.1B23.1x 172x / —+151%+26% $1,130 (31 rec)
COHR US6" InP + modules $326$63.8B8.1x 85x / —+77%+17% $418 (27 rec)

CUR_MKT_CAP converted at TWD 32 / JPY 150. IQE 1FY EPS not used (loss-making, P/S 5.1x, YTD +831%). 2455/3081/4971 FY27E P/E uses Bloomberg BEST_EPS 2FY. 3081 TTM sales NT$2.20bn vs mcap NT$272bn is the number that matters: the market is paying for FY28 (BEST sales NT$10.5bn, +4wk +NT$1.09bn).

How to read the three Taiwan epi names

聯亞 LandMark 3081 — the priced-for-perfection expression

全新 VPEC 2455 — current-production epi, mixed book

IET-KY 4971 — smaller, cheaper, US-fab option

Substrate layer — this is still the actual choke

Share-of-market numbers for InP wafers are not internally consistent across brokers (AXT 19–70%, SEI 31–60%, JX “about 40% with SEI”). Use the qualitative fact — three names, China-license risk on one of them — and do not underwrite a precise share.

Sell-side that actually moved the debate

DateHouseTypeLoad-bearing point
16 Jul 2026Citi研报-foreignFirst full InP laser S/D model. Industry chips 279m → 1.3bn by 2028 (+66% CAGR) still leaves EML 30/20/11% short. AXTI+SEI wafer ramp is the swing factor. LITE TP $1,100, +15% extra FY27 price, EPS to $21.18. CPO not delayed.
31 Jul 2026Nomura / 华泰行业 + 点评AXT Q2 InP “very strong”; Huatai: InP >$30m, GM 45%, backlog >$100m. Nomura prefers JX / SEI on China-license grounds.
2 Jul / 8 JulCiti / Nomura研报-foreignSEI 3.1× substrate; JX Buy, 7–10× capex, TP ¥4,800.
22 Apr 2026MS / Fubon / MOPS研报-foreign + 公告LandMark 1Q GM 54.8%; capex to NT$13.15bn; SEI 5-yr LTA. MS EW, TP 2,850 — already a “pause” call four months ago.
17 Apr 2026Goldman Sachs研报-foreignOptical TAM 9× to $154bn. Coverage universe includes 3081, 2455, 5016, 5802.
17 Aug 2026招商通信点评Same-day as the UDN clip. LITE UHP CW “far behind demand” is why they signed the AXT LTA; COHR 6" InP yield better than 3"; EML backlog into 2028/29; CPO scale-out now, scale-up 27H2.
CN 研报 on 2455/3081/4971AlphaEngine研报-CNZero recent company notes. Same finding as other TW non-semi names: mainland brokers do not write 3081/2455/4971. Foreign + local TW (MS, Fubon, KGI) is the library.

X · last 7 days

Chatter is real and clustered around the UDN reprint plus the LITE/COHR quotes. Original Taiwan-handle discussion of 全新 / 聯亞 / IET is sparse. A Bitget $AXTI cluster is promo.

DateHandleClassWhy it mattersLink
16 Aug@pequityresearchPrimary reprintThe clip that started this update. 26k views.post
12 Aug@pequityresearch / @PhotonCapEarnings quoteCOHR: InP is the primary constraint; no external laser sales.post
11 Aug@pequityresearchEarnings quoteLITE found additional substrate from AXTI.post
16 Aug@SemiconsightAnalystAXTI license mix: >50% Q2 already China-domestic; LITE/COHR deposits do not revenue until 2027.post
17 Aug@paurooteriJP synthesisAdds the LandMark–SEI LTA and IET US fab to the UDN frame.post
11 Aug@pequityresearchJPM APACInvestors want JX InP 20–30× by FY29 vs mgmt 7–10×.post

Do not use: low-engagement claim that China “removed” InP export controls (contradicted by Semiconsight / LawnChairFund).

What would break this

  1. Q4 hike does not stick — module makers refuse the >10% and GM at 3081/2455 rolls over in 4Q/1Q prints.
  2. AXTI US export licenses flood, or Tongmei HK listing / China-domestic mix makes Western lock-ups less scarce than the tape thinks.
  3. SEI + JX wafers actually show up in 2027 at the high end of the 3–10× slides, and UHP CW / EML prices roll.
  4. CPO / NPO scale-up slips past 27H2 and 1.6T pluggable demand cools. (CPO delay alone is not enough — pluggables still eat InP.)
  5. LandMark 2027 capacity 2.5× misses, or China 73% mix becomes a policy problem.

What to watch next

Date / windowItemWhy
~10 Sep 2026TW August monthly revenue (2455 / 3081 / 4971)Does the Jul inflection at VPEC continue? Does LandMark keep the H1 run-rate?
Sep 2026 ECOCLITE / COHR / PhotonLink / ELSCiti’s LITE catalyst window. Any change in UHP CW / EML lead times.
AXTI Nov Q3First US InP license? GM into the 50s? Deposit revenue still 2027?The fragile-choke check.
IET 2026 year-endTexas phase-2 mechanical completionArticle’s “今年完工” vs company’s early-2027 language.
OngoingIndium / red-phosphorus commentary (JX utilisation)If the Japan wafer slide is materials-constrained, 3081’s SEI LTA is more valuable, not less.

Source ledger

本页用于研究记录,不构成投资建议。Prices are a 17 Aug 2026 Bloomberg snapshot and will move.